Ignalina NPP announced a tender (1221 Project)

24 April,
2019
 Ignalina NPP announced a tender (1221 Project)

On 12 April 2019 Ignalina NPP announced a tender for the procurement of 110/6 kV transformer substation, two 110 kW overhead lines connection to 110 kV electricity transmission network design and project implementation supervision services (1221 Project).

The main aim of 1221 project is to ensure reliable power supply to Ignalina NPP consumers and reduce power consumption in the course of Ignalina NPP dismantling by constructing and commissioning new transformer substation.

By announcing this tender Ignalina NPP initiated an important stage of the energy cost reduction project to be completed in 2022.