Decommissioning projects

  Ignalina NPP decommissioning activities are co-financed by European Union


Current Projects

 project code  project name implementation period
B1 Interim Spent Fuel Storage Facility (ISFSF)
  • Contract signing - 12/01/2015
  • Construction commencement - 02/09/2009
  • Commercial operation - 04/05/2017
  • Fuel transportation completion 2022 III q.
В2/3/4

Solid Waste
Management
and Storage Facilities (SWMSF)

  • Start - 30/11/2005
  • Completion date - 19/04/2019
2206

INPP Unit 1 Turbine Hall Equipment Decontamination and Dismantling (D&D) Project license documents development, Project B9/1

  • Start - 22/11/2007
  • Completion date - 28/11/2013

Equipment dismantling under Project B9/1

  • Start - 21/10/2011
  • Completion date - 31/12/2019 /completed
2213

INPP Unit 2 Turbine Hall Equipment Decontamination and Dismantling (D&D) Project license documents development, Project B9/1(2)

  • Start - 14/09/2011
  • Completion date - 31/10/2013
  • Updated license for D&D received- 18/06/2014

Equipment dismantling under Project B-9/1(2)

  • Start - 01/07/2014
  • Forecast completion - 22/06/2021
B9/2

Block V1 Equipment Dismantling & Decontamination

  • Start - 14/01/2009
  • Completion of the first phase - 27/12/2013
  • The second phase will start after 2023
2214

Block D2 Equipment Dismantling and Decontamination

 
2203

INPP Building A1 Equipment Dismantling and Decontamination Design Development

  • Start - 01/05/2013
Performing dismantling works
  • Completion - 2034
2207

Unit D1, D0 Equipment Dismantling and Decontamination Design Development

  • Start - 03/06/2013
  • Completion - 15/09/2015
Performing dismantling works  
 2210 Dismantling and decontamination of A2 and V2 unit equipment  
  • Completion of Phase 1 - 2029
  • Start of Phase 2 - 2032, Completion of Phase 2 - 2035
B19 Landfill Facility for Short-lived Very Low Level Waste
  • Start - 29/12/2007
B20 Upgrade of Bitumised Waste Vaults  
  • Contract for the 1st stage 04/10/2018
B25

Near Surface Repository for Low and Intermediate Level Short-lived Radioactive Waste

  • Start - 23/10/2009
2103

Engineering and licensing for R3 and radioactive waste interim storage facility

  • Start - 07/2017
  • Forecast completion date - 15/02/2033
  Deep geological repository
  • Start - 2019
  • Forecast completion - 2078

 